Zeta Energy Battery Manufacturing Labs

Houston, TX
12/29/2023

Major cleanroom and dry room renovation with logistically challenging preparations for Phase II of project. Scope includes cleanrooms, dry rooms, architectural, HVAC, environmental and humidity monitoring, and interstitial piping relocations.

Read More

Northrop Grumman

Linthicum Heights, MD
12/29/2023

Furnished and installed architectural package for ISO7 semiconductor cleanroom. Scope included walls, ceilings, doors, windows, HEPA filters, and raised plenum floors.

Read More

Micron Semiconductor RMF Project

Boise, ID
12/29/2023

Installation of 75,000 SF of raised plenum flooring.

Read More

Sanofi

12/29/2023

We completed a 420 SF cold room with a temperature control of 2C to 8C. This room is used for material products storage in the building.

Read More

Alcami

12/29/2023

We completed a 800 SF cold room with a temperature control of 2C to 8C with a typical set point of 5C. This room is used for pharmaceutical storage. We used 4” insulated metal wall and ceiling panels.

Read More

NASA Greenbelt, MD

Greenbelt, MD
12/29/2023

Furnished and installed architectural package for ISO7 semiconductor cleanroom. Scope included walls, ceilings, doors, windows, HEPA filters, and raised plenum floors.

Read More

Verizon Plymouth Meeting, PA

12/29/2023

Completed demolition and fitout of data center. Including overhead grid system for critical systems attachment, as well as preparation of room for upgrades.

Read More

VA Logic Frederick, MD

Frederick, MD
12/29/2023

Installation of ceiling for semiconductor cleanroom.

Read More

Ferrera Candy, Inc.

Chicago, IL
12/29/2023

Multiple projects including installation of modular panels and architectural components for locker room and storage area; installation of insulated bot box foam panel enclosure for candy oven room; and installation of foam panel system for confectionary cooler.

Read More